Large Solid Asphalt Melting Tank Equipment
Product Description
For general melting volumes that are relatively large (2 - 15 t/h), a vertical coil structure is adopted; for smaller melting volumes (1 - 2 t/h), a horizontal tube bundle structure is used; for very small melting volumes (for testing purposes - 100 - 1000 kg/h), an electric heating structure is employed. While for block asphalt, an intermittent (discontinuous) tube bundle structure is generally used.
Main structure
The main structure consists of an asphalt tank body (upward straight and downward conical), a heat transfer oil heating coil (inner and outer coils and conical coil), a stirring system (motor reducer, support), and a support frame (upper and lower supports and columns). It is also equipped with electronic weighing sensors, digital thermometers, a bottom discharge mechanism, an asphalt filter, an asphalt buffer (receiving) tank, etc.
Working Principle
① The solid asphalt enters the melting zone through the feeding port. In the melting zone, the coil pipe is supplied with heat transfer oil, and under the action of the high-temperature heat transfer oil, the asphalt is heated, melted, and mixed by the agitator to enhance heat transfer and ensure uniform heating; high-quality liquid asphalt is pressed into the secondary heating zone, while the slag material enters the conical storage slag area.
② After the asphalt is heated and melted in the melting zone, under the pressure of the subsequent asphalt, it enters the secondary heating zone from the bottom for further heating, dehydration, and sedimentation of impurities; when the asphalt liquid level in the secondary heating zone reaches the discharge port position and its temperature meets the process requirements, the qualified asphalt is continuously and stably discharged from the discharge port, passes through the asphalt filter, and is transported by the insulated asphalt pump to the liquid asphalt storage tank.
③ At the bottom of the asphalt melting tank, there is a liquid asphalt discharge valve and an inspection hole (manhole). When cleaning is needed, open the liquid asphalt discharge valve, and through the asphalt pump, the liquid asphalt is sent to the buffer tank; after confirming that the liquid asphalt has been completely discharged, start the bottom slag discharge mechanism to discharge the settled impurities. Repeat this operation several times until no impurities are discharged, then close the sewage valve, and the sewage is completed; when maintenance is needed, maintenance personnel can enter through the bottom manhole.
④ Add a temperature measuring point at the outlet of the asphalt melting tank to keep the asphalt temperature within the set range. Through this temperature measuring point, control the opening degree of the heat transfer oil inlet valve, control the melting speed of the solid asphalt and the temperature of the liquid asphalt, and avoid asphalt aging due to overheating.