200m³ Liquid Asphalt Storage Tank
Solutions to Key Challenges in Raw Material Storage
Ensuring Production and Operational Reliability
Engineering Selection and Site-Specific Solutions
I. Basic Parameters (200 m³ effective capacity)
・ Type: Vertical atmospheric fixed-roof storage tank (standard for asphalt storage)
・ Dimensions (typical): Inner diameter Φ6.5 m, shell height ≈6.0 m; total volume 210–220 m³, effective volume 200 m³
・ Design pressure: Atmospheric (–0.5 to +2 kPa)
・ Design temperature: 180°C; Operating temperature: Base asphalt 140–160°C; Modified asphalt 150–170°C
・ Materials: Tank shell Q235-B; Heating coils: 20# seamless steel pipe
II. Tank Structure
1. Tank walls: Wall thickness 8–10 mm; tank bottom 8–10 mm; tank roof 6 mm.
2. Heating system
o Standard: Thermal oil coil heating (coils arranged inside the tank, connected to an external thermal oil heater; prevents localized coking and aging of the asphalt)
o Alternative: Electric heating (for small tanks; generally not recommended for 200 m³ capacity); direct open-flame heating is strictly prohibited.
3. Insulation layer: 100–150 mm high-density rock wool or aluminum silicate; outer cladding of 0.5 mm color-coated steel or aluminum sheet to prevent heat loss. 4. Ancillary Accessories
o Manhole (tank top), breather valve, overflow port, vent/drain port
o Level gauge (radar / differential pressure type), multi-point temperature sensors (bottom, middle, and top of the tank)
o Discharge outlet (low-level outlet at the tank bottom to facilitate complete asphalt drainage), sampling port
o Agitation system (agitation is recommended for modified asphalt storage tanks to prevent sedimentation and stratification)
o Lightning and static grounding system (grounding resistance ≤ 10Ω)
III. Safety and Process Essentials
Asphalt flash point is approximately 230°C; the operating temperature must strictly not exceed 180°C to prevent oxidation, aging, and fire risks.
Tank farm: Fire-containment dike; asphalt-sand cushion layer at the tank bottom; tank foundation requires settlement monitoring in compliance with GB50341 standards.
Operation:
o Filling: Preheat the tank body before introducing hot asphalt to prevent solidification caused by a cold tank.
o Shutdown: Maintain insulation temperature after stopping the feed; do not allow the temperature to drop directly. Fully drain the asphalt from the tank for long-term shutdowns.
Maintenance: For tanks containing high-temperature asphalt, maintenance procedures must include cooling, ventilation, and gas testing; entering the tank while it is hot is strictly prohibited.
Comparison with Other Storage Tanks
Basic Selection Guidelines